Saturday। 20 June। 2026
আগামীর সময়
Saturday। 20 June। 2026
Agamir Somoy
  • Latest
  • Bangladesh
  • Business
  • District
  • World
  • Environment
  • Entertainment
  • Sports
  • Lifestyle
  • OP-ED
  • Chattogram
  • Misc
  • Success Story
BN
  • Latest
  • Bangladesh
  • Business
  • District
  • World
  • Environment
  • Entertainment
  • Sports
  • Lifestyle
  • OP-ED
  • Chattogram
  • Misc
  • BN
লোড হচ্ছে…

Chief Editor & Publisher: Abdus Sattar Miazi

Editor: Mustafa Mamun

Agamir Somoy English Logo
About UsContactTerms of ServicePrivacy PolicyTeam

EDB Trade Centre (Level-6 &7) 93 Kazi Nazrul Islam Avenue Karwanbazar, Dhaka-1215.

Contact: +880 9666 771010

Advertise: +880 1755 651164

[email protected]

© 2026 | Dainik Agamir Somoy. All rights reserved.

আগামীর সময় Bangladesh

Nine Years Have Passed

Work Yet to Begin on Three Government Schools Near Dhaka

Hamid-uz-Zaman
agamir somoy
Published: 20 June 2026, 15:54
Work Yet to Begin on Three Government Schools Near Dhaka

Graphics: Agamir Somoy generated by AI

The government had undertaken an initiative to establish 10 government secondary schools in various areas adjacent to Dhaka in an effort to ease the pressure on the capital's prestigious schools. However, the failure to conduct a feasibility study for the project proved to be a fundamental flaw from the outset. As a result, nearly nine years have passed, and work has yet to begin on three of the schools. Three others have achieved only 10 to 33 percent progress, while four have reached 88 percent implementation.

Under these circumstances, the project's cost has escalated from 670 crore to approximately 803 crore taka, an increase of about 133 crore taka. Additionally, the timeline has been extended by seven years, now set to run until June 30, 2027. Beyond the financial and temporal setbacks, students are being deprived of the project's benefits in a timely manner. The initiative is now being regarded as a severely failed project.

These findings emerged in the draft of the intensive monitoring report by the Implementation Monitoring and Evaluation Division (IMED).

In this context, the report has recommended high-level review through the Ministry of Education and the implementing agency.

The report stated that the obstacles to project implementation must be identified and swiftly resolved. Furthermore, for future projects of this nature, feasibility studies must be made mandatory to identify land selection, land acquisition, project costs, and implementation risks in advance.

Abul Mansur Md. Faizullah, former secretary of IMED, told Agamir Somoy: "IMED's recommendations should certainly be taken into consideration. Delays in project implementation are wasting both time and money, while the benefits of a well-intentioned initiative are not being realized. Strengthening project monitoring is essential. There is no room for wasting taxpayers' money through the negligence of those involved. Those responsible must be identified and held accountable."

According to IMED sources, the project was originally scheduled for implementation between July 2017 and June 2020. The deadline has since been extended in three phases, now pushed to June 2027. Yet project progress remains disappointing.

The report noted that no feasibility study was conducted before the project was initiated. Had such a study been carried out, many of the land acquisition challenges and adversities could have been largely avoided. However, the absence of a feasibility study led to an abnormally prolonged period for land identification and acquisition. Consequently, the desired progress according to the project's work plan could not be achieved, necessitating multiple extensions of the project timeline.

Additionally, while the Revised Development Project Proposal (RDPP) includes project descriptions, objective verification indicators, verification means, critical assumptions, goals, objectives, outputs, and inputs, it lacks year-specific time indicators. For instance, there are no specified numbers for computer and computer equipment procurement, laboratory equipment, office equipment, educational materials, furniture, electrical equipment, or other procured items. This constitutes a significant deficiency in the DPP's formulation.

The report further states that overall, the secondary school establishment project can be considered a complete failure due to its slow pace, unplanned site selection, and the inefficiency of the implementing unit. The administrative incompetence of project officials and the lack of proper oversight are the project's fundamental weaknesses. Failure to acquire land on time, sluggish tender processes, and inadequate monitoring have continuously extended the project's duration. Nearly nine years have passed since the project's approval as of mid-2026, yet not a single school's construction has been fully completed, and the physical progress of this high-cost project is truly disappointing.

The project is being implemented by the Directorate of Secondary and Higher Education. Officials from the directorate said that the project document only specified areas for school establishment, without identifying specific plots of land. This has led to various complications.

Work Yet to Begin on Three Schools

Construction has not yet commenced on Khilkhet Government Secondary School and College in Khilkhet, Eastarchal Government Secondary School and College in Rupganj, and Purba Norasinghpur Government Secondary School and College in Savar.

Three Schools at 10-30 Percent Progress

Jalkuri Government Secondary School and College in Signboard area of Narayanganj, Khoddaghoshpara Government Secondary School and College on Chittagong Road, and Satarkul Government Secondary School and College in Badda remain at just 10-30 percent implementation progress.

Four Schools at 88 Percent Completion

Bilamalia Government Secondary School and College in Hemayetpur, Savar; West Dhi Government Secondary School and College in Keraniganj; Lakuria Para Government Secondary School and College in Dhamrai; and Banshbari and Pathalia Government Secondary School and College in Nabinagar have achieved 88 percent progress.

Dhaka government school project delayBangladesh school construction cost overrunIMED report 2026Secondary school project failure BangladeshEducation project feasibility study negligence
    শেয়ার করুন:
    advertisement
    advertisement
    Brazil Dominates Haiti 3-0 to Claim Top Spot in Group C

    Brazil Dominates Haiti 3-0 to Claim Top Spot in Group C

    20 June 2026, 09:30

    Record-Breaking Early Goal Powers Morocco Past Scotland 1-0

    Record-Breaking Early Goal Powers Morocco Past Scotland 1-0

    20 June 2026, 09:13

    USA Beats Australia 2-0, Clinches Knockout Spot in World Cup

    USA Beats Australia 2-0, Clinches Knockout Spot in World Cup

    20 June 2026, 10:03

    Broiler chicken Tk150 per kg, eggs Tk 110 per dozen

    Broiler chicken Tk150 per kg, eggs Tk 110 per dozen

    20 June 2026, 10:37

    Is Your Daily Vitamin Habit Harming Your Health?

    Is Your Daily Vitamin Habit Harming Your Health?

    20 June 2026, 11:17

    Fresh Water Turning into Air: Alarming Satellite Images Reveal Crisis

    Fresh Water Turning into Air: Alarming Satellite Images Reveal Crisis

    20 June 2026, 11:38

    Fraud Ring Hijacks Tk 30,000 Crore Chattogram Monorail Project

    Fraud Ring Hijacks Tk 30,000 Crore Chattogram Monorail Project

    20 June 2026, 11:08

    Gold prices fall again

    Gold prices fall again

    20 June 2026, 10:57

    Locals 5 Lakh, Rohingya 15 Lakh – The Alarming Impact on Cox's Bazar

    Locals 5 Lakh, Rohingya 15 Lakh – The Alarming Impact on Cox's Bazar

    20 June 2026, 14:07

    Obama Gets Emotional, Tears in Eyes at Wife's Speech

    Obama Gets Emotional, Tears in Eyes at Wife's Speech

    20 June 2026, 12:37

    Iran’s Supreme Leader Says He Dislikes Deal With U.S., but Allowed It

    Iran’s Supreme Leader Says He Dislikes Deal With U.S., but Allowed It

    20 June 2026, 15:26

    Iran's Foreign Minister Heads to Switzerland for Talks with the US

    Iran's Foreign Minister Heads to Switzerland for Talks with the US

    20 June 2026, 12:20

    The World's Densest Refugee Camps: 64,000 People Per Square Kilometre

    The World's Densest Refugee Camps: 64,000 People Per Square Kilometre

    20 June 2026, 15:09

    Israel-Lebanon Talks to Take Place in Washington Next Week

    Israel-Lebanon Talks to Take Place in Washington Next Week

    20 June 2026, 13:23

    Israel, Hezbollah Agree to Fragile Ceasefire in Lebanon

    Israel, Hezbollah Agree to Fragile Ceasefire in Lebanon

    20 June 2026, 11:29

    advertiseadvertise