Adani Power has reduced its electricity supply to
Bangladesh. Although the company’s Godda power plant in Jharkhand had been
supplying nearly 1,500 megawatts of electricity, its average supply has stood
at 1,000 megawatts for several days. During the day, the supply is between 800
and 850 megawatts while at night it reaches between 1,100 and 1,300 megawatts.
The reduction in Adani’s power supply for more than a month
amid the country’s severe electricity crisis has drawn widespread critici...