Rooppur ready, power may be added to national grid Tuesday

Rooppur Nuclear Power Plant project at Iswardi of Pabna. File photo.
After a long wait and various complex tests, the first unit of the Rooppur Nuclear Power Plant is finally ready for power generation. If everything goes well, the electricity generated experimentally will be connected to the national grid from Tuesday.
Several officials of the Bangladesh Atomic Energy Commission and the project, speaking on condition of anonymity, confirmed the matter to Agamir Somoy.
According to the officials, the first unit will be connected to the grid for a few hours on Tuesday. During this time, there are plans to supply up to 240 megawatts of electricity to the national grid. After that, the connection will be disconnected from the grid and the necessary tests of the power plant will be conducted. If everything goes well, it will be reconnected to the grid after final approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA).
According to project sources, preliminary preparations for grid connection were taken last Sunday, but it was postponed due to vibration. Later, after the vibration level was brought down to the prescribed level, the first unit is now fully ready.
When asked, Mahmudul Hasan, Chairman of the Bangladesh Atomic Energy Regulatory Authority, told Agamir Somoy that their approval must be obtained before connecting to the grid. This approval will be given only after ensuring all types of safety.
Two officials of the Atomic Energy Commission said the capacity and tests of the reactor, turbine, and other important equipment have already been successfully completed. So far, their plan is to finally connect Rooppur to the power grid on November 21. The relevant departments have been informed accordingly. However, before that, it will be temporarily connected to the grid on an experimental basis so that there is no problem in the final connection. At that time, BAERA's approval will be required. Before that, no approval is needed.
Engineer Rezaul Karim, Chairman of the Power Development Board (PDB), told Agamir Somoy on Sunday, "The national power grid is ready. We have been asked to have a representative present when Rooppur's electricity is connected to the grid. We have kept that preparation."
According to sources, the government plans to hold a formal ceremony on the occasion of the grid connection. Prime Minister Tarique Rahman and Russian President Vladimir Putin are scheduled to join that event virtually. In that case, the electricity may be formally connected to the grid before or after November 21.
Electricity will be generated by turning the turbine with steam produced by the specified thermal energy generated from nuclear fuel. Initially, the power plant will be operated at only 3 percent capacity. Later, once it is gradually raised to 30 percent, it will be possible to supply electricity to the national grid. At that time, about 300 megawatts of electricity will be available.
After that, various tests will be conducted. It will take about 7-8 months to increase power generation to full capacity. Commercial production will begin after experimental power supply. However, once electricity goes to the grid, Bangladesh will become the world's 33rd country in the list of nuclear power-producing countries.
Earlier, in October 2023, after nuclear fuel arrived at the project area, the Rooppur power plant was recognized as a nuclear facility. With the receipt of fuel, Bangladesh's name entered the list of countries with nuclear power.
Once the first unit of Rooppur is connected to the national grid, Bangladesh will join the list of nuclear power-producing countries as the world's 33rd country. This will add a new source of power generation as well as begin a new chapter in Bangladesh's capability in nuclear technology.
The plant has two units with a capacity of 1,200 megawatts each. Of these, each unit will generate a minimum of 1,150 megawatts of electricity. Excluding the power plant's own use of up to 120 megawatts, at least 1,030 megawatts will be supplied to the national grid.
According to the terms of the contract, if less electricity is supplied than this, the Russian contractor will have to pay a penalty. The two units together will add at least 2,060 megawatts of electricity to the national grid.
Work on the second unit is also in full swing. If everything goes well, nuclear fuel may be loaded into this unit next year. Once the electricity from both units is connected to the grid, load shedding will decrease and a huge amount of foreign currency will be saved in fuel imports. The price of nuclear electricity will also be lower compared to oil- and coal-based electricity.
The Rooppur Nuclear Power Plant is the largest single project in the country's history, with financial and technical assistance from Russia. The project is being implemented by the Atomic Energy Commission under the Ministry of Science and Technology. The state-owned organization Nuclear Power Plant Company Bangladesh Limited (NPCBL) is handling its operation.
The original deadline for the project was December 2025, which has been extended twice to June 2028. According to the original agreement with Russia, the project's euro or dollar contracting costs did not increase even though the time was extended. However, due to the increase in the dollar exchange rate in the local market, the project cost in taka has increased by about Tk 26,000 crore. Currently, the estimated cost for implementing the project has been set at Tk 1,38,686 crore.